Bawany Air Products Limited (the Company) is a public limited company incorporated in Pakistan on August 16, 1978. The Company is listed on the Pakistan Stock Exchange Limited. It operates as an investment company — investing in, acquiring, holding and dealing in shares, stocks, debentures, bonds, obligations and securities, and acquiring shareholdings in businesses.

Subsidiary

Alman Seyyam Sugar Mills

The sections below cover Alman Seyyam Sugar Mills (Pvt.) Limited — a wholly owned subsidiary acquired by Bawany Air Products Limited. ASSML is developing a sugarcane crushing plant at Dera Ismail Khan; figures and progress notes are from the project briefing.

Wholly owned subsidiary of Bawany Air Products Limited · Dera Ismail Khan

Overview

Key capacities

Design figures for the Alman Seyyam plant from the progress briefing. Not proof the plant is fully operating.

10,000 TCD
Cane crushing capacity
18 MW
Turbine power generation
2 Boilers
Steam boilers
4 Mills
Mills in mill house
94 t/h
Steam per boiler
45 t/h
RO water treatment
  • Boiler pressure 87 bar
  • Total steam (approx.) 190 t/h
  • Mill drive design 15,000 TCD

Site

Site overview

Alman Seyyam Sugar Mills (Pvt.) Limited · Dera Ismail Khan

Item Detail
Main gate Site entry and plant identity
Jamia Mosque Near central gate · separate ladies arrangement
Offices & engineers’ hostels Beside mosque · officer / engineer housing
HOD hostel In progress · more than 60% complete
Labour barracks Separate barracks built
Main office Central system for key departments

Main office departments

  • PD Office
  • GM Project
  • DGM Mechanical
  • DGM Production
  • HOD Electrical
  • Administration
  • Accounts

Wholly owned subsidiary of Bawany Air Products Limited. Some public filings spell the company Alman Seyyem. Update this file to change the name site-wide.

Video

Project progress video

Site progress and development briefing for Alman Seyyam Sugar Mills, Dera Ismail Khan — from the main gate through the plant.

Facilities

Facility status

Click a section to open its details. Only one section stays open at a time.

Illustrative concrete construction photo. Not the DI Khan site. Illustrative
Item Detail Status
Main gate Plant entry Ready
Jamia Mosque Ladies arrangement provided Ready
Engineers’ hostels & offices Next to mosque Ready
HOD hostel Construction >60%
Labour barracks Separate housing Built
Main office PD, GM Project, DGM Mechanical, DGM Production, HOD Electrical, Admin, Accounts Active
HOD hostel >60%

Schedule

Key dates & targets

Spoken milestones from the briefing. Year is not always stated.

  1. 01

    Site & accommodation

    Gate, mosque, hostels, barracks, main office. HOD hostel >60%.

  2. 02

    Cane yard

    31 Oct · year not stated

    Outer sub-base 60–70%. Inner yard civil in progress. Target ready: 31 October*.

  3. 03

    Cane handling equipment

    2 weighbridges ready. Carriers tested. Jack drives, 1 feeding chain, cutter balancing, shredders pending.

  4. 04

    Mill & process houses

    4 mills in place. Rotary screen, lubrication, planetary cooling pending. 3 Robert evaporators done. 2 of 4 vacuum filters done.

  5. 05

    Boilers & steam

    Plummer blocks: 27 Sep* · year not stated

    Steam to header. Hydro tests complete. Fans, plummer blocks, HP turbine pipe, lagging, ash system pending.

  6. 06

    Water treatment

    RO 45 t/h complete with EDI. Tanks lined. Ready for HP boiler water.

  7. 07

    Power house & turbine

    Panels, cables, VFDs done. Turbine ≈80%. Grouting after Chinese engineer advice.

  8. 08

    Outstanding deliveries

    Cooling tower: 25 Sep* · year not stated

    Vacuum filters, 1 centrifugal, cooling tower, 2nd dryer/grader, packing/warehouse kit, jack parts, boiler fans, pressure parts.

  9. 09

    Crushing start target

    Reported target · year not confirmed

    If ordered equipment arrives on time: crushing in 3rd week of November, with other area mills. Spoken season ≈2024 (not confirmed).

Target

Target: crushing season

If ordered equipment arrives on time, remaining work is to be finished for a crushing start in the third week of November. The briefing aims to bring the plant into operation for the upcoming crushing season.